Reserve fund and maintenance planner
Last checked 21 November 2026
Plan your block's repairs and reserve fund. Work out what your block will need over the next 30 years, what it will cost, and how much each flat should pay into the reserve fund (sinking fund) to cover it.
Test version. Your first plan is free, including the printed plan, the seller's summary and the spreadsheet. Each year after that, open your saved plan for the annual review. The annual update (£19.99 a year) rolls the plan forward and reprices it. The AGM management pack (£39.99 a year) adds charts, budget against spending, a verdict, recommendations and a page to print for the AGM. Both are free while the planner is being tested.
Who it's for
- Directors of a right to manage company, a residents' management company, or a company the leaseholders own that holds the freehold.
- Leaseholders checking whether their landlord's reserve fund demand is reasonable.
- Sellers who need a summary of the fund for a buyer's solicitor.
Before you start
- Check your leaseA reserve fund can only be collected if the lease allows it. If yours doesn't, or you're not sure, the planner still shows the work and the costs, but not a reserve contribution.
- England onlyBlocks of 4 to 20 flats, up to four storeys.
- Not cladding or fire safety remediationIt doesn't cover cladding or other fire safety work under the Building Safety Act 2022.
- Guide figures, not a surveyA chartered surveyor should inspect the building at least every three years, and before any major works, to assess each item in the plan and prepare or update the programme of works. This is a planned maintenance inspection and report, not a full building survey or a schedule of condition. The planner is for the updates in between.
Windows that belong to the leaseholders
Where the lease makes each leaseholder responsible for their own windows, the landlord can't collect reserve money for them, and windows replaced one flat at a time end up mismatched. There are four ways to deal with it.
- Who is responsible for the windows?Check the lease.
- The landlord or management company?Yes: they go into the reserve fund like any other itemNo: go on
- 1Vary all the leases togetherWrite to every leaseholder, with the Section 20 notices or before them, asking whether they agree to the windows becoming the block's responsibility. If everyone agrees, one solicitor varies all the leases at the same time, which keeps the cost per flat down.
- Did everyone agree?Yes: the windows go into the plan and the reserve fundNo: go on
- 2A majority application to the tribunalThe First-tier Tribunal can vary all the leases (Landlord and Tenant Act 1987, Section 37). For 8 flats or fewer, all or all but one must agree. For 9 or more, at least 75% must agree and no more than 10% object. The tribunal must also be satisfied the aim can't be achieved unless all the leases are varied.
- Is there enough support?Yes: apply to the tribunalNo: go on
- 3The opt-in window schemeThe same contractor, specification and scaffold for all the windows. Each leaseholder who opts in agrees and pays the contractor directly. The landlord or management company isn't party to those agreements and doesn't handle the money.
- 4Leave it with each leaseholderEach leaseholder repairs and replaces their own windows under the lease. Many leases need the landlord's consent for alterations, which may allow a matching type and style to be required. That depends on the lease.
Letter to the leaseholders about the windows
Send this to every leaseholder at the same time. It works best sent with the Section 20 notices for the major works, or before them, so the windows can be included in the consultation once the leases are varied.
How the figures are worked out
- Each part of the building has a usual life. The planner uses the middle of the published range. You can change any date if you know better, for example from your lift or fire alarm engineer's report.
- Anything in poor condition, or where you don't know, is treated as due now. Essential work (anything letting in water or affecting safety) goes in year 1. Other overdue work is spread over years 2 to 5: outside work in year 2 under one scaffold, inside work in year 3, and the services in years 4 and 5.
- Jobs that need the same scaffold are put in the same year, so you pay for the scaffold once. A job is brought forward by up to three years to share a scaffold, never put back.
- Ladders are only allowed for short, low-risk work. Otherwise a tower or scaffold is priced for the job.
- Prices come from published price guides, averaged, with older figures brought up to date using the Construction Output Price Index for housing repair and maintenance, produced by the Office for National Statistics, the government's official statistics body. Prices include VAT and are reviewed every three months.
- Every job shows how its cost is made up: the work, scaffold or tower, site set-up costs (preliminaries), surveyor's fees at 10%, and an allowance for the unexpected (contingency) of 10%.
- Routine yearly costs such as cleaning, insurance, and lift and fire alarm servicing stay in the yearly service charge, not the reserve fund.
- Items not due in the next 30 years, such as a slate roof with a long life left, are left out of the contributions.
Why today's prices are enough, as long as you update the plan every year
The plan uses today's prices, with no guess at future inflation. Each year you update it, the prices are updated too, so the contributions rise with building costs.
For example, if a new roof would cost £50,000 today, next year it might cost £51,500, and the contributions go up a little to match. By the time the roof is due, the fund has grown with the cost, so the money is there when it's needed. The roof is usually the biggest item, but the same is true of every part of the building.
This only works if the plan is updated every year. No interest is assumed on the fund.
The prices and assumptions used
The law in brief
- A reserve fund can only be collected if the lease allows it.
- Reserve contributions are held on trust for the leaseholders (Landlord and Tenant Act 1987, Section 42). The RICS Code says the money should be kept in a separate bank account. Interest is taxed at the basic rate, and no tax return is needed if the trust's income is £500 or less in a year.
- Contributions normally stay in the fund when a flat is sold.
- Works costing any leaseholder more than £250 need a Section 20 consultation.
- Contributions must be no more than is reasonable. Leaseholders can challenge a demand at the First-tier Tribunal (Landlord and Tenant Act 1985, Section 27A).
More on your rights, and a letter asking for the fund's figures, in Service charges and major works.
Questions and answers
Does our lease allow a reserve fund?
Only your lease can tell you. Look in the service charge clauses for words such as reserve, sinking fund or future expenditure.
How much is enough?
The law doesn't set a figure. Contributions must be reasonable. The planner gives a guide figure for your block.
What happens to my contributions if I sell?
They normally stay in the fund for the block.
Must the money be in a separate account?
The law requires it to be held on trust. The RICS Code says it should be in a separate bank account. A law requiring a designated account was passed in 2002 but has not been brought into force.
Is the interest taxed?
Yes, at the basic rate. No tax return is needed if the trust's income is £500 or less in a year.
Can the landlord spend it on anything?
No. It can only be used for the costs it was collected for under the lease.
Can I challenge my landlord's demand?
Yes, at the First-tier Tribunal under Section 27A, before or after paying.
Why 30 years?
Roofs, lifts and windows often come round less than once every 10 years. Thirty years catches most of them, so you start saving now rather than facing one large bill later.
How often should we update it?
Every year, and whenever work is done or a surveyor or engineer reports on the building.
Do we still need a surveyor?
Yes. A chartered surveyor should inspect the building at least every three years, and before any major works, to assess each item in the plan and prepare or update the programme of works. This is a planned maintenance inspection and report, not a full building survey or a schedule of condition.
Need expert help?
The Leasehold Advisory Service gives free advice on service charges and reserve funds. For repair and maintenance works of this size, a chartered surveyor can usually design, specify and run the job. Bring in a specialist only where the work needs one, such as a structural engineer or a lift consultant. See when to get expert help.
Find a chartered surveyor or accountant
A chartered surveyor should inspect your block at least every three years to prepare or update the programme of works. We can put you in touch with one near you.
Tell us about the block and we'll pass your details to a chartered surveyor who covers your area. They will contact you directly with their fee. You're under no obligation to instruct them.
This is an introduction to a specialist professional. It is not a recommendation or an endorsement.
Introductions are free. Held to Account is not paid by the professionals it introduces you to. If that changes, this page will say so.
What this doesn't cover
- Cladding, external wall and other fire safety remediation under the Building Safety Act 2022.
- Blocks of more than four storeys, or more than 20 flats.
- The inside of individual flats.
- Wales, Scotland and Northern Ireland.
Sources
- Landlord and Tenant Act 1987, Section 42: service charge contributions held on trust
- Landlord and Tenant Act 1987, Section 37: variation of leases by a majority
- Landlord and Tenant Act 1985, Section 19: reasonableness
- Landlord and Tenant Act 1985, Section 27A: the tribunal
- RICS Service Charge Residential Management Code, 4th edition
- RICS professional standard: Planned preventative maintenance
- HMRC: service charge trusts under Section 42
- ONS: Construction Output Price Indices
- CIBSE: indicative economic life expectancy (lifts and services)